Commodore Barry Bridge work (per DRPA): To facilitate painting, work will continue until 2022. Work platforms will be installed 3 feet beneath the bridge in various locations reducing the vertical clearance to 178 ft. above mean high water at the edge of the navigable channel (187 ft. center of channel). Phase 1 – NJ approach girder and deck truss spans has been completed. Phase 2 – PA approach girder and deck truss spans, has been completed. Phase 3 – Cantilever truss span, scheduled to commence in early 2020 and conclude in 2022. Mariners should exercise caution.